NATIONAL CENTER FOR ATMOSHPERIC RESEARCH
GAU and SUR Summary of Funding and Uses for FY 2000
9/30/00
  Total FY 2000 Committed Uncommitted
Funding Sources Funding Funding /1 Carryover Carryover
GAU       67,097              14,397                       -                  52,700
Uses of Funds
No activity                -  
Funds available, but not approved for spending       67,097   
 Previous FY  FY 2000
Reconciliation of GAU Uses   Approved Expenditures Expenditures Available
No activity                       -                           -  
   
   Total  FY 2000  Committed  Uncommitted
Funding Sources  Funding  Funding  /1  Carryover  Carryover
SUR     389,179            246,823                 142,356
Uses of Funds
No activity                -  
Total Uses                -        
Available     389,179   
Funds available and approved for spending   (196,266)
Funds available, but not approved for spending     192,913
 Previous FY  FY 2000
Reconciliation of SUR Uses   Approved Expenditures Expenditures Available
ISS and L2D2 Upgrades & Mnt. (appr: 03/25/97)       57,395            (48,293)                      9,102
Electra Aircraft Upgrades & Mnt. (appr: 08/21/98)       27,432               (8,121)                       -                  19,311
GPS Flight Management System (appr: 02/04/00)       34,434 [1]                       -                         -                  34,434
ISS, L2D2 & EMCC Computer System (appr: 05/01/00)         6,757                       -                 (6,757)                         -  
C-130 corrosion inspection (appr: 09/15/00)     168,213              (34,794)              133,419
    294,231            (56,414)            (41,551)              196,266
/1  FY 2000 Funding represents revenues received during the fiscal year.

[1]
Received permission to spend $34,434 commitments, bids came in higher.