| National Center for Atmospheric Research | |||||||
| CLIMATE SIMULATION LABORATORY | |||||||
| Summary of Funding and Uses for Quarter 2, FY 2002 | |||||||
| 3/31/02 | |||||||
| TOTAL | FY 2002 | COMMITTED | UNCOMM | ||||
| FUNDING | FUNDING | C/O | C/O | ||||
| Fund Sources | |||||||
| CMAP /1 | 14,216,761 | 7,732,000 | 6,435,667 | 49,094 | |||
| Fund Uses | |||||||
| Computer Leases/Maintenance /2 | 3,612,401 | ||||||
| Mass Storage Upgrades /3 | 1,165,598 | ||||||
| Committed for CSL Upgrades | 2,803,619 | ||||||
| Staff Costs /4 | 1,820,165 | ||||||
| Procurement Related Expenses | - | ||||||
| Other Operating Costs /5 | 214,499 | ||||||
| Available Balance | 4,600,479 | ||||||
| Total Uses | 14,216,761 | ||||||
| Notes | |||||||
| 1. | Estimated FY 2002 funding. | ||||||
| 2. | Includes $46,072 committed but not spent. | ||||||
| 3. | Includes $500,879 committed but not spent. | ||||||
| 4. | Includes $996,204 committed but not spent. | ||||||
| 5. | Includes $88,116 committed but not spent. | ||||||