  1. The time frames below are average time frames. Individual requirements may either lengthen or shorten the estimated lead time. If the requirement is an emergency or if it contains unusual requirements which may lengthen the procurement process, such as prequalification of sources or establishing and evaluating proposals using a source evaluation committee, please call the Contracts Office to discuss a realistic time frame for processing the requirement. If, after the requisition is sent to the Contracts Office, an unusual requirement is identified which may affect the lead time, the Contracts Office will contact you to discuss the unusual requirement and its affect on the lead time.

 

  2. The lead times stated below are based on NSF Cooperative Agreement approval requirements. If the funding source is other than NSF, call the Contracts Office to confirm agency approval requirements.
   
     
Dollar Threshold Time Frame* Contract Type
<$5,000 0-3 Days

All Except Construction
$5K-$10K 0-5 Days
3-5 Days
10-15 Days

 

Supply/Equipment
Services/Consultant
Construction/A & E

 

$10K-$25K 3-5 Days
3-5 Days
10-15 Days
Supply/Equipment
Services/Consultant
Construction/A & E

 

$25K-$100K 10-15 Days
15-20 Days
15-20 Days

 

Supply/Equipment
Services/Consultant
Construction/A & E

 

>$100K 15-20 Days**
15-20 Days**
20-30 Days**
Supply/Equipment
Service/Consultant
Construction/A & E

 

* Expressed in working days from date of receipt of a completed purchase requisition and statement of work until contract award. Lead times do not include delivery times. These are tentative timeframes and subject to change depending on complexity and magnitude of project.

** NSF approval requirements will add 30 days to the schedule as stated above. NSF requires approval of contracts for construction, architect/engineering services, supplies, aircraft leases and equipment with a cost over $250,000.00. Except for construction and architect/engineering services, Contracts for services do not require NSF approval at any dollar level.